07-12-2011 10:58 AM
We just made a tremendous upgrade from 4.05 to 4.4... (YIKES)
One of the problems that I'm seeing is that I no longer have the ability to change the Std Cost on the Inventory Maintenance screen, and in order to go through Std Cost Adjustment, EVERYONE has to be completely out of the system...
There's got to be a better way...
Re: Another way to change Std. Cost in Version 4.40.0.5
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
07-15-2011 11:38 AM
Really? there's no other way to get this done?
What about automatically changing the Std Cost to read "Last Cost"?
Re: Another way to change Std. Cost in Version 4.40.0.5
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
07-15-2011 12:57 PM
You can call it whatever you want, but to change the field MAS knows as Standard Cost will require using the new procedures. You can, however, create a file with the item and the new standard cost and import it into the work files while everyone is on the system and then just run the register and update with folks off. (Assumes you own Visual Integrator)