MRP Double-Dipping?

Hello all,

We are just starting to learn about MRP in MAS 500 (v7.3), but I've quickly run into the problem of MRP "double-dipping" requirements.  In running MRP for a group of raw materials, MRP tries to place new PO's based on both the raw material demand (from "Calculate Projected Demand") while also including the actual demand from work orders that call out the raw material.  We end up with double demand.

 

How do you get around this?

 

Thanks,

smossman