I'm new to MAS and am looking to create a PO for a piece part that goes out for plating. Basically, we would machine the part in-house and give it a part number, then we want to send the part out to a plating house, have them plate it, and then bring it back in as a different part number. Is there a way to do this in MAS200 through the purchase order function? Thanks.
Re: Part numbers and Purchase orders
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
11-08-2011 08:34 AM
Welcome to the Sage Community!
This is very common and most people do one of two things.
1. Work Order - Create a work order, issue out the product and rework expense. When it is done do a completition and bring back into inventory. Do a purchase order for the plating and assign to work order.
2. Do a Bill of Materials production entry with the cost of plating as a misc. charge. You still do a work order for the plating but you cannot assign to Bill.
--------------------------------------------------------------------------
You have enemies? Good. That means you've stood up for something in your life.
Re: Part numbers and Purchase orders
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Highlight
- Email to a Friend
- Report Inappropriate Content
11-09-2011 05:01 AM
Thanks for the information. After discussing it with some of the people here, we think that one of these options will work well.