Part numbers and Purchase orders

I'm new to MAS and am looking to create a PO for a piece part that goes out for plating.  Basically, we would machine the part in-house and give it a part number, then we want to send the part out to a plating house, have them plate it, and then bring it back in as a different part number.  Is there a way to do this in MAS200 through the purchase order function?  Thanks.

Switcher
BigLouie
Posts: 2,689
Registered: 10-28-2008
0

Re: Part numbers and Purchase orders

Welcome to the Sage Community!

 

This is very common and most people do one of two things.

 

1. Work Order - Create a work order, issue out the product and rework expense. When it is done do a completition and bring back into inventory. Do a purchase order for the plating and assign to work order.

2. Do a Bill of Materials production entry with the cost of plating as a misc. charge. You still do a work order for the plating but you cannot assign to Bill.

Big Louie No MBA but BMOC
--------------------------------------------------------------------------
You have enemies? Good. That means you've stood up for something in your life.
unidentified user
dlewis0310
Posts: 2
Registered: 11-08-2011
0

Re: Part numbers and Purchase orders

Thanks for the information.  After discussing it with some of the people here, we think that one of these options will work well.